当前位置:网站首页>5、 Project management

5、 Project management

2022-06-23 08:38:00 Fallen bird

1、 project management

Examination site : Concept

Four factors of project success : Range 、 speed of progress 、 cost 、 quality

Four basic stages : Conceptual stage 、 The development phase 、 Implementation phase and completion phase .

Scope Management : Unclear definition of project scope is often the primary cause of project failure , Project scope management is the project plan 、 The basis of control , Project scope management determines the specific tasks of the project , Contribute to clear division of responsibilities and assignment of tasks . Input to the scope definition includes the project charter 、 Project scope management plan 、 Organizational process assets 、 Approved change request

Project plan : Is to coordinate the preparation of all project plans 、 Documents guiding project implementation and control , The key part is the project introduction 、 Project description 、 Project management and technical process 、 And work progress information and budget information

Project master plan : Scope plan 、 Scope of work definition 、 Activity definition 、 Resource requirements 、 Resource Planning 、 Activity sequencing 、 Cost estimates 、 Schedule and cost plan

Project support plan : Quality plan 、 Communication plan 、 Human resources plan 、 Risk plan 、 Purchase plan

Schedule management

Configuration Management : Lies in the use of configuration identification 、 Configuration control 、 Configuration status and configuration audit , Establish and maintain the integrity of work products .

Configuration management work results : The requirements document 、 Design document 、 Source code and test cases .

Documents generated by project management and institutional support processes : Work plan 、 Project quality report and project tracking report

Cost management : Estimated cost 、 Specify budget 、 Control the cost

2、PERT chart

Examination site : Draw... According to the topic information PERT chart , Calculate critical path , Total construction period , Relaxation time .

Draw... According to the topic information PERT chart

According to the dependency , Draw a precursor map , Complete each task node in the precursor diagram according to the following figure . The earliest time Forward thrust Calculation , Latest time Backstepping Calculation .

The first time

Time limit

End at the earliest

Mission

At the latest

Relaxation time

At the latest

Serial tasks The longest time Our route is the key route , The earliest and latest time of the critical route is the same , The sum of critical path duration is the total duration .

Slack time in parallel tasks ( Non critical route ), Relaxation time = At the latest - The first time