当前位置:网站首页>The answer skills and examples of practical cases of the second construction company are full of essence

The answer skills and examples of practical cases of the second construction company are full of essence

2022-06-26 01:47:00 Direct employment from the ground

The second grade exam begins today , Let's take a look at the case analysis summary and answer skills of practical questions , Analyze the idea of the person who created the question , Make it easier for everyone to score !

Case study

Bid price 100 element /m, Base price 120 element , float 15% The Contractor shall be responsible for .

Major events 1 Seasonal rainstorm occurs , Shutdown X God , Loss X Ten thousand yuan , Claim submission manager , The supervisor rejects the application .

Major events 2 Especially bad weather occurs ( Describe what the storm is ), Cause downtime 6 God , Stay at the employer's request 4 Employees , happen 1 Ten thousand yuan , The Contractor shall clean up the site after the rainstorm 2 Ten thousand yuan , Loss of employees and machinery of the contractor 10 Ten thousand yuan , The Contractor shall compensate for the construction period 6 God , use 13 ten thousand .

Major events 3 The Subcontractor is particularly heavy rain , Claim the construction period from the supervisor 6 God , For employees , The supervisor rejected the request

【 problem 】

problem 1∶ Major events 1 Whether the supervisor's practice is correct , reason ?

problem 2∶ For major events 2. Whether the Contractor's claim period is reasonable , The supervisor can review the cost of the construction period ?

problem 3∶ For major events 3, Whether the supervisor's practice is correct ?

problem 4∶ During the construction period, the price rises to 150 element /m, What is the final settlement price ?

【 analysis 】

problem 1 The supervisor's practice is correct . Cause seasonal rainstorm is not a force majeure factor , do

Being an experienced engineering manager should be predictable , So it is caused by seasonal rainstorm

Loss of construction period and cost , By the contractor .

problem 2∶ The duration of the claim 6 The weather is reasonable Especially bad weather and rainstorm are force majeure factors , Therefore, the construction period is postponed . What can be claimed against the employer is 3 Ten thousand yuan , At the request of the employer 4 Famous staff 1 Ten thousand yuan ; For site cleaning after rainstorm 2 Ten thousand yuan . Due to the loss of personnel and machinery during the rainstorm 10 Ten thousand yuan does not belong to the claim category , The Contractor shall be responsible for it

problem 3∶ The supervisor's practice is unreasonable , The subcontractor may claim the construction period from the general contractor , It is caused by force majeure , Therefore, the construction period can be postponed 6 God .

problem 4∶ During the construction period, the price is , The higher base price shall be used to calculate the risk range value agreed in the contract , namely 120×(1+15%)=138 element /m So the price ∶150-138=12 element /m; So the final settlement price is ∶100+12=112 element /m

Answer skill

Read the questions first , Answer the question again

Every exam , The supervisor will hand out the papers five or ten minutes in advance , The first thing to do is to read the questions , How to read it ? After getting the test paper , Look at each question , Work out the questions you are familiar with and you will know the answers at a glance , Including case questions , The answer to the question can be answered without looking at the information , Write down the main points on the paper first . Why do this ? After entering the examination room to answer questions , You start when your head is clear 10 More minutes , After the real answer , You're having a few problems , My mind must be confused , Chaos , At that time, I told you that you would get all the questions wrong , Because you're out of your mind . So I'm talking about this technique , It can effectively guarantee your accuracy and scoring rate .

Dialectical thinking , For many reasons

Answer why , from 2 Start with , The first is the direct cause , The second is the indirect cause

Okay , That's all for today's sharing , I wish you all the best in the exam !