[software cost consulting] information project bidding process and precautions
2022-06-24 01:40:00 【Hopestarit】
One 、 Software project bidding process
Overview of the overall process
- Read the tender
- Start a union
- Pre bid clarification
- Demand analysis , The overall plan , answer SOC, Write technical proposal , offer
- review 、 Decision making
- Bid submission
- Post bid clarification
1、 Read the tender
—— What information needs to be learned from the tender ?
- Company situation , Bidding background
- Scope of tender
- Compliance instructions
- Mode of delivery
- Way of quotation
- Bid submission time
- Bid evaluation method
- Technical proposal requirements
—— What information other than the scheme needs to be output ?
- The customer is in pain
- Main risks
- Competitive analysis
- Bidding strategy
- other
3、 Label clarification
—— Why ask for clarification ?
- In intensive reading 、 When reading through the tender , For terms that are not clearly described or have vague interface in the tender document , Or there are clauses that are very unfavorable to the bid ( Such terms may have been guided by friends ), Need to clarify to the customer .
- Bidding stage , Bid clarification is a formal channel for communication with customers , We should also take clarification as an effective means of active marketing and customer guidance .
—— Reply principle
- Try to use closed questions instead of open questions ;
- Pay attention to the tone of the question and the English expression ;
- Do not include the company name in the question ;
- Eliminate the problems that can be solved in the project team ;
- Submit clarification questions to the customer ;
- Review and clarify issues , And the responsible person of the customer shall submit the questions , Get clarification reply .
4、SOC reply
——SoC Reply rules and guidelines
- Writing ideas : The way to answer questions . In terms of writing alone , Brevity is the main way to answer questions , For some statements such as ”state”,“how”, “describe”, “indicate”, “explain” etc. , We must give a detailed description , Highlight the word expression .
- Format requirements : Fully Compliant(FC)/ Partially Compliant(PC) / Not Compliant(NC). If the customer knows SoC Reply format , Just use the customer's template .
- Content requirements :SoC In reply , It is necessary to carefully understand SoC The terms require , At the same time, it is necessary to understand the SoC Reply method , Different customers SoC The requirements are different , Accordingly SoC Response strategies are also different .
—— Reply strategy
- Try to increase the number of replies “ Satisfy ” Terms , Reduce responses “ Partial satisfaction ” and “ dissatisfaction ” Terms .
- SoC Reply to the referenced attachment document , For easy reference .
- The response should be constructive , Even if the customer's requirements cannot be met , We should also fully understand the needs of customers , Reassure customers with constructive answers ( Such as providing road signs 、 Alternatives, etc ).
- Sensitive to 、 Clauses that may affect the bid evaluation , And I can't answer “ Satisfy ” Of , You can reply in vague terms , Avoid antagonizing the bid inviter , It also paves the way for later negotiations .
5、 The project design
The overall scheme design includes two parts , The first is the professional scheme of each professional module ; The second is the overall plan after summary
- scene : database , virtualization , Disaster recovery backup ,HPC, Video surveillance ……
- Storage product selection :IOPS, bandwidth , Capacity , Interface , Hard disk ……
- Storage software selection : Remote Replication , snapshot , Hierarchical storage , Delete and compress ……
- Network product selection : Switch ( type , Number of ports , Quantity, etc ), Wave division ……
- Current network connection is compatible : operating system , Upper software , Current network , Old equipment ……
- Upper layer software selection : Backup (CV,NBU…), Video surveillance (milestone…)
6、 To configure , offer
7、 Bid submission documents
—— Comprehensive plan
- The opening : Introduce the industry proposition , Describe the customer's current network , Demand, etc , Reveal customer pain points ;
- The main body : Focus on customer concerns , Introduce the customized solutions provided by our company , Show the benefits to customers , Reflect our differentiated solutions and product highlights , Including product and service solutions ;
- ending : Provide specific business cases , Show the benefits to customers
- Technical proposal : Refer to each technical proposal template
——SOC reply
- Configure quotation
- business , Service materials
- Other information provided to customers : Product description , Qualification certification, etc
Two 、 Relevant concepts
1、 bid
It is a concept corresponding to bidding , It refers to that the tenderer shall respond to the tenderee's specific or unspecified invitation , According to the requirements specified in the bidding documents , The act of actively submitting tender documents to the tenderee at the specified time and place for the purpose of winning the bid .
2、 Tendering
It is a highly targeted project , Planned 、 Important activities with preparation , Commonly used internationally 、 Organized market trading behavior , It is a kind of project in trade 、 goods 、 How to buy and sell services , Relative to the bid , It is called bidding . Bidding refers to the tenderee ( Buyer ) Issue tender announcement or invitation to tender , Describe the project to be tendered 、 goods 、 Scope of services 、 Bid section ( Package ) Divide 、 Number 、 bidder ( seller ) Qualification requirements, etc , Invite specific or unspecified bidders ( seller ) At the appointed time 、 The act of bidding in accordance with certain procedures .
3、 Tender
It refers to the tenderer's specific proposal to the tenderee to conclude the contract according to the tenderee's requirements , It is an alternative scheme provided to the tenderee . The bidding documents are divided into production and operation bidding documents and technical bidding documents . Production and operation bidding documents include project bidding documents 、 Contract tender 、 Product sales bid 、 Labor tender ; The technical bid includes the bid for scientific research projects 、 Bid for technology introduction or transfer .
4、 Winning the bid
It means that the bidder is determined by the tenderee as the contract signing object of the bidding project according to the legal process , In general , The bidder who wins the bid , It shall receive the notification of award issued by the tenderee .
5、 Bidding
Based on the traditional bidding method , That is, the seller sells the goods to the highest bidder . There should be more than three valid bidders ( Including three ) Or more than three companies that substantially respond to the bidding documents ( Including three ).
3、 ... and 、 Bidding ( Excluding prequalification stage ) Provisions on the time limit of each process in
(1) Sale period of bidding documents : Not less than 5 Japan .
(2) Time limit for submission of tender documents : No less than... From the date of issuance of the bidding documents 20 Japan .
(3) Time for clarification or modification of bidding documents : Clarification or modification of the bidding document affects the preparation of the bidding document , The bid shall be submitted within the bid deadline 15 Made a few days ago .
(4) Time limit for raising and responding to objections to the bidding documents : The deadline for bidding 10 Recently proposed .
(5) Time limit for reply to objections to the bidding documents : From the date of receipt of the objection 3 Reply within days , Before you reply , Suspend tendering and bidding activities .
(6) The time limit for returning the bid security when the bid document is withdrawn before the deadline for bid submission : From the date of receipt of the written withdrawal notice from the bidder 5 Intraday .
(7) The time of bid opening : At the same time as the deadline for bid submission .
(8) Time limit for raising bid opening objection : On the spot .
(9) Time limit for reply to bid opening objection : On the spot .
(10) Start time of publicity of bid winning candidates : From the date of receiving the bid evaluation report 3 Intraday .
(11) Publicity period of bid winning candidates : No less than 3 Japan .
(12) Time limit for raising objections to bid evaluation results : During the publicity period .
(13) Time limit for reply to objection of bid evaluation results : From the date of receipt of objection 3 Intraday .
(14) Contract signing period : Within the period of bid validity and from the date of issuing the letter of acceptance 30 Intraday .
(15) Validity of bid security : Consistent with the bid validity period .
(16) Time limit for return of bid security : At the latest after the contract is signed 5 Intraday .
(17) The time limit for the bidder or other interested parties to file a complaint : From the date of knowing or ought to know 10 Intraday .
(18) The time limit for the administrative supervision department to handle complaints : From the date of receipt of the complaint 3 Decide whether to accept or not within working days , And from the date of acceptance 30 Processing within working days , Need to check 、 testing 、 Identification of 、 Expert review , The time required does not count .
(19) Propose to extend the bid validity period : The bid evaluation and award cannot be completed within the bid validity period .
(20) Time limit for written report on bidding and tendering : From the date of determining the successful bidder 15 Intraday .
(21) The time limit for public announcement of illegal acts of tendering and bidding : From the date when the decision on handling illegal acts in tendering and bidding is made 20 Make external record announcement within working days , The time limit for announcement of records of illegal acts is 6 Months , After the expiration of the announcement , Transfer to the background to save . The qualifications of the parties to the tender and bid shall be restricted according to law ( Qualifications ) And other administrative decisions , The period of limitation identified is longer than 6 Months , The duration of the announcement shall be determined by itself .
3、 ... and 、 Relevant laws and regulations
《 Bidding Law 》 The first 20、34、46、47 strip ;
《 Regulations for the implementation of the bidding law 》 The first 16、21、22、26、35、44、54、57、60、61 strip ;
The third section of the text is 14 Article the contract shall be signed for 《 Bidding law for construction projects 》 The first 62 strip ;
The third section of the text is 19 The time basis for the extension of the bid validity period proposed in clause is 《 Interim Provisions on bid evaluation committee and bid evaluation methods 》 The first 40 strip ;
The third section of the text is 21 Article the time limit for public announcement of illegal acts of tendering and bidding shall be based on 《 Interim Measures for announcement of records of illegal acts in tendering and bidding 》 The first 6、9 strip .
边栏推荐
- Typescript type system
- S2b2c e-commerce platform in the pharmaceutical and medical industry enables enterprises to grasp differentiated competitive advantages and improve supply chain efficiency
- Digital case show ‖ made in China for the first time! Tencent cloud tdsql landed in Zhangjiagang bank and worked together to build financial business
- Implementation of automatic triggering of inward delivery order after outward delivery order PGI in SAP inter company sto process
- Easynvr background channel list timing request touchstreamclient interface optimization
- NJS triggers system command operation
- Property management source code based on wechat applet
- How does smart digital operation get through offline collection and online marketing?
- Code practice | ground extraction with logo-loam
- Textplus - reverse engineering of textplus
猜你喜欢
![[SQL injection 13] referer injection foundation and Practice (based on burpseuite tool and sqli labs less19 target platform)](/img/b5/a8c4bbaf868dd20b7dc9449d2a4378.jpg)
[SQL injection 13] referer injection foundation and Practice (based on burpseuite tool and sqli labs less19 target platform)

I, a 27 year old female programmer, feel that life is meaningless, not counting the accumulation fund deposit of 430000
![[flutter] comment utiliser les paquets et plug - ins flutter](/img/a6/e494dcdb2d3830b6d6c24d0ee05af2.png)
[flutter] comment utiliser les paquets et plug - ins flutter

【Flutter】如何使用Flutter包和插件

It's too difficult for me. Ali has had 7 rounds of interviews (5 years of experience and won the offer of P7 post)
![[SQL injection 12] user agent injection foundation and Practice (based on burpsuite tool and sqli labs LESS18 target machine platform)](/img/c8/f6c2a62b8ab8fa88bd2b3d8f35f592.jpg)
[SQL injection 12] user agent injection foundation and Practice (based on burpsuite tool and sqli labs LESS18 target machine platform)
随机推荐
How to make a fixed asset identification card
Oracle sqlldr quick import and sqluldr2 quick export
Interviewer: why does the new generation memory need two survivor zones?
Tencent host security (cloud mirror) arsenal: a sword to kill mining Trojans binaryai engine
Eight common errors in programming
Coding compass -- creating a software factory like a flowing cloud
Coordinate system "slang" in GIS world
Typescript type system
The Mars rescue plan has been released. The year of the tiger is limited to dolls waiting for you!
How to build a pagoda panel web site on Tencent ECS?
How to access the server through the fortress machine? What if the fortress cannot access the server?
Application of "popular science" UAV and video technology in fire scene
Intensive use of glusterfs 4.1
NFS operations and deployment
AES encryption analysis of CNKI academic translation
[technology planting grass] talk about the system design and architecture of large-scale shopping platform
Build a smart pole visual intercom system through an intelligent gateway
Mobile direct payment, super convenient
Echo framework: implementing timeout Middleware
"Ai+ education" and "Ai education": one for education and the other for Education