当前位置:网站首页>PMP practice once a day | don't get lost in the exam -7.23
PMP practice once a day | don't get lost in the exam -7.23
2022-07-23 16:58:00 【Greenrad】
!PMP Latest exam notice !
1. Tentatively on 2022 year 6 month 25 The morning of Hold the first batch of exams ( I have finished the exam ).
2. Tentatively on 2022 year 7 month 30 On the afternoon of Sunday Hold the second batch of exams .
The first batch of today's exam
Come on , Go ashore
distance 【 The second batch of 】 Exams and
7 God
everyday 5 Avenue PMP Exercises help you get ashore PMP!!!

1. The company plans to start new projects in new fields , The project team is based on industry models and industry data , To estimate a new project, what estimation method did the project team use ? ( )
A. Top down estimates ;
B. Analogous estimating ;
C. Parameter estimation ;
D. Expert judgment
【 answer 】C
【 analysis 】" Parameter estimation is a method based on historical data and project parameters , An estimation technique that uses an algorithm to calculate cost or duration .
The title stem mentioned “ Industry models and industry data ”"
2. If the estimated cost of some operations in a work package is $1,500, And it should be finished today . However, in fact, the cost is used $1,350, And the work is only completed 2/3, The cost deviation is :" ( )
A.+$150;
B. -$150;
C. -$350;
D. -$500
【 answer 】C
【 analysis 】PV=1500,AC=1350,EV=1500*2/3=1000,CV=EV-AC=1000-1350=-350.
3. According to the Earned Value Report , The project has been completed 30%. A recognized “ Known unknowns ” There's a risk , The project manager has to choose to use the risk reserve and take some necessary activities to solve the problems caused by the risk . What should he do next ?"( )
A. The progress benchmark should be changed , The cost benchmark remains unchanged ;
B. The cost benchmark should be changed , The progress benchmark remains unchanged ;
C. Schedule and cost benchmarks should not change ,
D. Schedule and cost benchmarks should change , To reflect the new work
【 answer 】C
【 analysis 】 For known risks , Use emergency reserves . Emergency reserve is included in cost benchmark and schedule benchmark . The unknown is the risk , Use management reserves . Management reserves are not included in the cost benchmark , Are included in the total budget .
4. After identifying the risks that will have a negative impact on the project budget , The project manager needs to determine whether the remaining emergency reserve is sufficient , Which of the following tools or techniques should the project manager use ?"( )
A. Reserve analysis ;
B. Deviation and trend analysis ;
C. Emergency analysis ;
D. SWOT analysis
【 answer 】A
【 analysis 】 Reserve analysis includes reserve analysis of time and funds , Analyze the reserves reserved for the smooth progress of the project .
5. Your project management system experience tells you that an incorrect response to cost variance may cause quality or schedule problems , Or unacceptable project risks . You are holding a team meeting to discuss the importance of cost control . Many of your team members are new to project management . In order to introduce this important topic to you , You state that cost control focuses on :( )
A. Factors that will cause changes to the cost baseline , Ensure that changes are beneficial ;
B. Form an approximate estimate of the cost of the resources needed to complete the project ;
C. Assign full cost estimates to work items ;
D. Establish a cost baseline
【 answer 】A
【 analysis 】 Source :PMBOK The project cost control includes :…… Influence the factors causing the change of cost benchmark ; choice A
边栏推荐
猜你喜欢

Eureka笔记

CNCF基金会总经理Priyanka Sharma:一文读懂CNCF运作机制

Tan Zhangxi, director of risc-v Foundation: risc-v has gradually expanded from the edge to the center

低代码搭建校园信息化管理系统案例分析

Basic auth plug-in based on apisik authorizes Minio file upload function

【Web漏洞探索】SQL注入漏洞

小米集团副总裁崔宝秋:开源是人类技术进步的最佳平台和模式

Squeeze-and-Excitation Networks(挤压和激励网络)

Solve data functions should return an object (property "visible" must be accessed with "$data.visible")
![[note] linear regression](/img/71/7c1255e94f08cc0eab2ca32977f29d.png)
[note] linear regression
随机推荐
MongoDB数据库+图形化工具下载安装及使用
Taishan Office Technology Lecture: layout drawing analysis of paragraph borders
[C language] structure, enumeration and union
快速学会使用文件的权限
Microcomputer principle and technical interface practice in class
泰山OFFICE技术讲座:段落边框的布局绘制分析
[note] linear regression
软件体系结构
SSD: Single Shot MultiBox Detector
中国化NFT?NFR横空出世
The first stage of basic knowledge of numpy data analysis (numpy Foundation)
Bag of Tricks for Image Classification with Convolutional Neural Networks(卷积神经网络在图像分类中的技巧)
【无标题】
面试官:生成订单30分钟未支付,则自动取消,该怎么实现?
JS之闭包
浏览器四大内核
银河证券网上开户,手机上开户安不安全
Acquisition of positional reliability in accurate target detection
Object.defineProperty方法、数据代理
securecrt 乱码