Key summary VII of PMP examination - monitoring process group (1)
2022-06-28 09:27:00 【The green flowers of Wang Li's family】
One 、 Control range
Input :
1. Project management plan
① Scope management plan
② Demand management plan
③ Change management plan
④ Configuration management plan
⑤ Range reference
⑥ Performance measurement benchmark
2. Project documents
① Register of lessons learned
② Requirements document
③ Demand tracking matrix
3. Performance data
4. Organizational process assets
Tools & technology
1. Data analysis
① Deviation analysis
② Trend analysis
Output :
1. Job performance information
2. Change request
3. Project management plan update
① Scope management plan
② Range reference
③ Progress benchmark
④ Cost basis
⑤ Performance measurement benchmark
4. Project file update
① Register of lessons learned
② Requirements document
③ Demand tracking matrix
a key :
1、 Control scope to prevent scope spread .
2、 Deviation analysis —— Used to compare benchmark with actual results , To determine whether the deviation is within the critical value range or whether corrective or preventive measures are necessary .
3、 Trend analysis —— To review changes in project performance over time , To determine whether performance is improving or deteriorating .
Two 、 Control progress
Input :
1. Project management plan
① Schedule management plan
② Progress benchmark
③ Range reference
④ Performance measurement benchmark
2. Project documents
① Register of lessons learned
② Project Calendar
③ Project schedule
④ Resource Calendar
⑤ Progress data
3. Performance data
4. Organizational process assets
Tools & technology
1. Data analysis
① Earned value analysis
② Iterative burnout diagram
③ Performance review
④ Trend analysis
⑤ Deviation analysis
⑥ Hypothesis analysis
2. Critical path method
3. Project management information system
4. resource optimization
5. Lead and lag
6. Progress compression
Output :
1. Job performance information
2. Progress forecast
3. Change request
4. Project management plan update
① Schedule management plan
② Progress benchmark
③ Cost basis
④ Performance measurement benchmark
5. Project file update
① Hypothesis log
② Estimation basis
③ Register of lessons learned
④ Project schedule
⑤ Resource Calendar
⑥ Risk register
⑦ Progress data
a key :
1、 Iterative burnout diagram —— It is used to track the work to be completed in the unfinished items of the iteration .
3、 ... and 、 Control the cost
Input :
1. Project management plan
① Cost management plan
② Cost basis
③ Performance measurement benchmark
2. Project documents
① Register of lessons learned
3. Project funding requirements
4. Performance data
5. Organizational process assets
Tools & technology
1. Expert judgment
2. Data analysis
① Earned value analysis —— Earned value analysis compares actual progress and cost performance with performance measurement benchmarks .
② Deviation analysis
③ Trend analysis
④ Reserve analysis
3. to complete performance index
4. Project management information system
Output :
1. Job performance information
2. Cost forecast
3. Change request
4. Project management plan update
① Cost management plan
② Cost basis
③ Performance measurement benchmark
5. Project file update
① Hypothesis log
② Estimation basis
③ cost estimation
④ Register of lessons learned
⑤ Risk register
a key :
1、EVM Benchmark the range 、 Integrate cost and schedule benchmarks , Form performance measurement benchmarks . It is for each work package and control account , Calculate and monitor the following three key indicators : Plan value (PV)、 Earned value (EV)、 actual cost (AC).
2、PV: The approved budget allocated for the planned work .
3、EV: Measured value of completed work ( An approved budget for work done ).
4、AC: The actual cost of performing the work .
5、BAC: Completion budget .
6、 Cost deviation (CV = EV – AC)、 Schedule deviation (SV = EV – PV)、 Deviation from completion (VAC = BAC – EAC)、SPI = EV/PV、CPI = EV/AC.
7、ETC: Budget needed to complete the remaining work .ETC=(BAC-EV)/CPI
8、EAC: Completion estimate .EAC = AC +(BAC – EV)、EAC = BAC/CPI
9、 to complete performance index ——TCPI=(BAC–EV)/(BAC – AC)、TCPI =(BAC – EV)/(EAC – AC)
Four 、 Control quality
Input :
1. Project management plan
① Quality management plan
2. Project documents
① Register of lessons learned
② Quality measurement index
③ Test and evaluation documents
3. Approved change request
4. Deliverables
5. Performance data
6. Business environment factors
7. Organizational process assets
Tools & technology
1. data collection
① Checklist
② checklists
③ Statistical sampling
④ The questionnaire survey
2. Data analysis
① Performance review
② Root cause analysis
3. Check
4. test / Product evaluation
5. Data performance
① Cause and effect diagram
② Control chart
③ Histogram
④ Scatter plot
6. meeting
Output :
1. Quality control measurement results
2. Verified deliverables
3. Job performance information
4. Change request
5. Project management plan update
① Quality management plan
6. Project file update
① Problem log
② Register of lessons learned
③ Risk register
④ Test and evaluation documents
a key :
1、 Checklist —— Checklists help to manage and control quality activities in a structured way .
2、 checklists —— checklists , Also known as counter , Used to arrange various items reasonably , In order to effectively collect useful data on potential quality problems .
3、 Pareto Diagram : Identify a few important causes of most problems .
4、 Control chart —— Control charts are used to determine whether a process is stable , Or whether it has predictable performance .( Control boundaries ±3 Sigma , Seven point principle ).
边栏推荐
- Test cases for learning the basic content of software testing (II)
- 1182: group photo effect
- Importerror: no module named image [duplicate] - importerror: no module named image [duplicate]
- 01-分布式系统概述
- RESTful风格
- 在本类私有属性直接使用?new()在使用!!!
- Common test method used by testers --- orthogonal method
- 数字人行业爆发在即,市场格局几何?
- 1182:合影效果
- 静态代码块永远先执行? 格局小了!!!
猜你喜欢

学习阿里如何进行数据指标体系的治理

Decision table method for basic content learning of software testing (2)

The Cassandra cluster reinstalls and starts from the node. An error is reported. There is an existing solution

1182:合影效果

JDBC connection database (MySQL) steps

Postman interface test

Calculation of stock purchase and sale expenses

Common tools for interface testing --postman

From knowledge to wisdom: how far will the knowledge map go?

1182: effets de la photo de groupe
随机推荐
JDBC connection database (MySQL) steps
01 distributed system overview
Rman Backup Report Ora - 19809 Ora - 19804
创建多线程的方法---1创建Thread类的子类及多线程原理
全链路业务追踪落地实践方案
JMeter -- interface test 2
异常
Import and export of a single collection in postman
Basic knowledge of hard disk (head, track, sector, cylinder)
手机买同业存单基金开户选哪家证券公司比较好,比较安全呢
How to solve the problem of port number occupation
PMP考试重点总结六——图表整理
The digital human industry is about to break out. What is the market pattern?
构造方法绝不是在new()之后就立马执行!!!!!
Implementation of single sign on
Loggerfactory uses log4j Parameter introduction of properties
Data mining modeling practice
Test cases for learning the basic content of software testing (II)
1182:合影效果
English translation plug-in installation of idea